2907499 - Cost could not be determined for some or all materials of task

Symptom

When you valuate the project you would see this warning message.

Environment

SAP Business ByDesign

Reproducing the Issue

  1. Go to Project Management work center
  2. Choose the Projects view
  3. Choose project 
  4. Choose the Edit button
  5. Choose the Valuate button
  6. Here you can see the warning message Cost determined with errors for some or all materials of task

Cause

There is something not maintained and thus cost was not determined, there could be various reasons and the exact error can be seen in cost and revenue work center

Resolution

  1. Go to Cost and Revenue work center
  2. Choose the Projects view
  3. Choose the Project 
  4. Choose the View Plan Values button
  5. You can see here some of the project tasks are in Error status marked in Red color
  6. Choose project task and navigate to the Messages tab here you can see error message

  You need to take action as per the error or you can use this error or using the error search for respective KBA in helpcenter that can help solve your issue.

See Also

 2831120 - The Project Planned Cost Shows Zero After Maintaining Material in the Project

2907652 - Valuation of material XYZ in business residence ABC failed on DD-MM-YYYY