SAP Knowledge Base Article - Public

2643809 - How To Extend Resource Scheduler Demand Assignments To Multi-days

Symptom

Unable to extend Resource Scheduler Demand Assignments To Multi-days

Environment

SAP Cloud for Customer

Reproducing the Issue

  1. Go to Resource Scheduler Work Center
  2. Go to Demands view
  3. Select the demand and try to drag and drop
  4. You can only drag and drop for one day after the other

Cause

Necessary scoping question needs to be flagged to select Resource Scheduler demand Assignments To Multi-days

Resolution

  1. Go to Business Configuration Work Center
  2. Select Implementation Projects View
  3. Select Edit Project Scope button
  4. Go to Questions section
  5. Expand General Business Data
  6. Select Resource Scheduler
  7. Mark the question "Do you want the system to create assignments automatically till a demand is fulfilled?"

Complete Fulfillment allows the system to create assignments everyday until a demand is completely fulfilled, based on certain defined rules. This helps plan demands with long duration. The dispatcher does not have to create the assignments manually.

Please use 'Week-Detail' view to extend the assignment for next day

Keywords

Resource scheduler, demand, drag-drop, multiple days , KBA , demand , drag drop , resource scheduler , LOD-CRM-RES , Resource Scheduling , How To

Product

SAP Cloud for Customer 1805 ; SAP Cloud for Customer 1808