2643678 - LMS - How to change the schedule of a course

SAP Knowledge Base Article - Public

2643678 - LMS - How to change the schedule of a course

Symptom

Admin wants to change the schedule of a course.

Environment

SAP SF Learning Management System

Resolution

1. On the Scheduled Offering Level, go to Related >> Segments

2. Choose the segment that you want to change the date

3. You will find a start date and end date there. You can modify that to the correct date/time.

Segment edit Date.PNG

Keywords

LMS, Scheduled Offering, Change Date, Change Time, Date, Time, Segment, Segment time, segment date, modify, schedule, item, item schedule , KBA , LOD-SF-LMS-ITE , LMS Items , LOD-SF-LMS-SCH , Scheduled Offerings , Problem

Product

SAP SuccessFactors Learning 1511 ; SAP SuccessFactors Learning 1602 ; SAP SuccessFactors Learning 1605 ; SAP SuccessFactors Learning 1608 ; SAP SuccessFactors Learning 1611 ; SAP SuccessFactors Learning 1702 ; SAP SuccessFactors Learning 1705 ; SAP SuccessFactors Learning 1708 ; SAP SuccessFactors Learning 1711 ; SAP SuccessFactors Learning 1802 ; SAP SuccessFactors Learning 1805 ; SUCCESSFACTORS LEARNING 1808 ; SuccessFactors Learning 1207 ; SuccessFactors Learning 1210 ; SuccessFactors Learning 1302 ; SuccessFactors Learning 1305 ; SuccessFactors Learning 1308 ; SuccessFactors Learning 1311 ; SuccessFactors Learning 1402 ; SuccessFactors Learning 1405 ; SuccessFactors Learning 1408 ; SuccessFactors Learning 1411 ; SuccessFactors Learning 1502 ; SuccessFactors Learning 1505 ; SuccessFactors Learning 1508