2597520 - Production Task ID are not in Sequence

SAP Knowledge Base Article - Public

2597520 - Production Task ID are not in Sequence

Symptom

In a Production Order you will notice that Production Task ID's are not in sequence i.e. Supply Task ID and Make Task ID are not in sequence.

Environment

SAP Business ByDesign

Reproducing the Issue

1. Go to Production Control workcenter and Production Order View.
2. Select the Production Order and in Details check the Tasks tab.
You will notice that the Supply Task ID and Make Task ID are not in sequence.

Cause

Task ID is proposed by system randomly during run time.

Resolution

You will have to follow Start Feasibility in Tasks tab i.e. start the task that is Green.
Once this Task is completed system will set the Start Feasibility to Green for the next task in sequence.

Keywords

Production Task, Production Order, Make Task, Supply Task, Start Feasibility, Sequence , KBA , production task , supply task , production order , make task , sequence , start feasibility , AP-PE-TSK , Production Task , Problem

Product

SAP Business ByDesign all versions