2512490 - How to add custom due date for step - Onboarding

SAP Knowledge Base Article - Public

2512490 - How to add custom due date for step - Onboarding

Symptom

  • I would like to change due date for particular step for particular process.
  • How to add custom due date for step.

Environment

  • Onboading

Resolution

To add custom due date for some step you should do the following steps.

As example, we will add custom due date for first step for Onboarding process.

  1. Go to Super Admin site, Processes
  2. Click "Onboarding" process, "Step 1". 
  3. Click option "Assign Due Dates".
    2017-08-01_11-17-39.jpg
  4. Click "Add Due Date"
  5. Please fill out all properties:
    - Count of days (work days, weeks, month, years)
    - Before or After
    - Select date which will be taken as initial date

 In the screenshot below, you could see that new due date will be calculated as 5 calendar days before start date.

2017-08-01_11-22-59.jpg

 

List of initial dates is taken from Data Dictionary. There are all keys with type "Date".

You could few custom due dates, which will be calculated according to filters.

Keywords

  • Due Date
, KBA , LOD-SF-OBD-ADM , Admin Tools, Settings, Permissions , How To

Product

SAP SuccessFactors Onboarding all versions