2440798 - MRP does not considered forecast into account.

SAP Knowledge Base Article - Public

2440798 - MRP does not considered forecast into account.

Symptom

When running the MRP you have noticed the system did not consider a particular forecast.

Reproducing the Issue

  1. Go to Supply planning Work Center.
  2. Navigate to Products View.
  3. For a particular product select Run Planning --> Single Level BoM.

We observe that the system did not consider a particular Forecast and skipped it.

Cause

As the given forecast was firmed by an User, the system skipped it. The same behavior is applied for other documents such as Production Proposals.

Resolution

To have the Forecast considered, it is necessary to select the same and then select the option Undo Firm.

Keywords

KBA , AP-SDM , Supply and Demand Matching , How To