Symptom

You have done some activity immediate changes on the productive system after created the XYZ change project  and now you want to carry those changes over to the existed change project. 

Cause

Update the XYZ change project after some immediate changes has been done on the productive system can prevent fine-tune inconsistence and data overwrite

Resolution

  1. Go to Business Configuration work center.
  2. Go to Implementation Project view.
  3. Click on the XYZ change project hyperlink title.
  4. On the XYZ Project overview click on the actions button.
  5. Select the Update Project from Production option.
  6. After the update is done, the change project should be consistent with the productive system.