2038616 - Error Message : Project stock order not created; all materials are non stock

SAP Knowledge Base Article - Public

2038616 - Error Message : Project stock order not created; all materials are non stock

Symptom

While creating Project stock order system throws an error message Project stock order not created; all materials are non stock.

Reproducing the Issue

  1. Go to Project Management work center.
  2. Choose Projects View.
  3. Choose Project XYZ (XYZ represents the Project ID).
  4. Chose Edit -> Project Plan.
  5. Go to the Products tab -> Products Overview sub tab.
  6. Here choose the Product and click on the Create Project Stock Order button system throws an error message Project stock order not created; all materials are non stock .

Cause

  1. From stock is not enabled in the planned material for which you want to create the Project stock order.
  2. Project Stock consumption is not scoped.

Resolution

Cause 1 : From stock is not enabled

  1. Go to Project Management work center.
  2. Choose Projects View.
  3. Choose Project XYZ (XYZ represents the Project ID).
  4. Chose Edit -> Project Plan.
  5. Choose project header or project task .
  6. Go to the Material subtab here you can see the From Stock check box should be enabled.

Cause 2 : Project Stock consumption is not scoped.

It means From Stock check box itself not available under material subtab.

CD 2034794 - From Stock Check Box is not Available.

Keywords

KBA , AP-PRP , Purchase Request Processing , How To

Product

SAP BUSINESS BYDESIGN 1611 ; SAP BUSINESS BYDESIGN 1705 ; SAP BUSINESS BYDESIGN 1708 ; SAP Business ByDesign 1402 ; SAP Business ByDesign 1405 ; SAP Business ByDesign 1408 ; SAP Business ByDesign 1411 ; SAP Business ByDesign 1502 ; SAP Business ByDesign 1505 ; SAP Business ByDesign 1508 ; SAP Business ByDesign 1511 ; SAP Business ByDesign 1602 ; SAP Business ByDesign 1605 ; SAP Business ByDesign 1608 ; SAP Business ByDesign 1702 ; SAP Business ByDesign 1711