SAP Knowledge Base Article - Public

1517140 - Error Message 'Enter Valid Activity' when Trying to Release the Time Sheet

Symptom

When you try to Save and Release a time sheet, system throws the error message Enter Valid Activity.

Note: The activity will be inputted by default when selecting the project task.

Reproducing the Issue

  1. Go to Home work center.
  2. Select Self Services view.
  3. Select Edit Time Sheet link.
  4. Enter the Project task and required time recoring.

System throws above error message.

Cause

In the fine tuning for Default time types, the configuration for service based time recording is initial. Therefore a message is raised as the default time type for service confirmation can not be determined.

Resolution

The missing pre-delivered defalut time type will be provided once the business option Payroll Processing with Time recording is in scope. As this scoping is currently missing in service based time confirmation on projects is not able to be done for all employees.

You can activate this business option in your solution to avoid this issue.

Keywords

KBA , AP-PRP , Purchase Request Processing , How To

Product

SAP BUSINESS BYDESIGN 1705 ; SAP BUSINESS BYDESIGN 1708 ; SAP Business ByDesign 1702