1626121 - Assigned Project Tasks are Missing in Time Sheet of an Employee

Symptom

You did record time for a particular project in the past. However, now the project task is missing in the Time Sheet.

Reproducing the Issue

  1. Go to the Project Management work center.
  2. Select Edit Time Sheet.
  3. Record time for a particular project task for a defined period.
  4. Save and release the time.

When you access the Time Sheet again, the project task name is missing in the Project Task column.

Resolution

The general system behavior is as follows:

  1. The visibility of the activity depends on the logon language. If your activity is in German language and if you are logged in with English, then it is possible that the activity may not appear in the Time Sheet.
  2. The visibility of the task depends on the project language. If your project and project tasks are maintained in German language and if you are logged in with English, then it is possible that the project/project task’s name may not appear in the Time Sheet.

Keywords

KBA , AP-PRO , Project Processing , How To