2695808 - /RPM/FICO_INT_PLANNING does not update all items

Symptom

  • You carry out Integration with program /RPM/FICO_INT_PLANNING for multiple portfolio items (e.g. by selecting a bucket or the whole portfolio). You notice that the financial planning data is only processed for some items but not all.
  • If you run the program for just one of the "missed" items, then the Integration and planning are carried out OK.

Read more...

Environment

  • SAP Portfolio and Project Management 6.1
  • SAP Portfolio and Project Management for SAP S/4HANA (PPM)
  • SAP Portfolio and Project Management in SAP S/4HANA (PPM)

Product

SAP Portfolio and Project Management 6.1 ; SAP Portfolio and Project Management for SAP S/4HANA all versions ; SAP S/4HANA all versions

Keywords

financial integration, plan costs, actual costs , KBA , PPM-PFM , Portfolio Management , Problem