2664696 - Production Order Actual Start Date/Time and Actual Finish Date/Time

Symptom

Production Order actual start date/time is expected to the first confirmation date/time, and actual finish date/time is expected to the final confirmation date/time. However, the actual start date/time and actual finish date/time is not explainable.


Read more...

Environment

  • SAP ERP Production Planning (PP)
  • SAP R/3
  • SAP R/3 Enterprise
  • SAP ERP Central Component
  • SAP ERP
  • SAP Enhancement package for SAP ERP
  • SAP Enhancement package for SAP ERP, version for SAP HANA
  • SAP S/4HANA, on-premise

Product

SAP ERP Central Component all versions ; SAP ERP all versions ; SAP R/3 Enterprise all versions ; SAP R/3 all versions ; SAP S/4HANA Cloud all versions ; SAP S/4HANA all versions ; SAP enhancement package for SAP ERP all versions ; SAP enhancement package for SAP ERP, version for SAP HANA all versions

Keywords

OPK4; Actual Start Date; Actual Start Time; Actual Finish Date; Actual Finish Time; Scheduled dates; CAUFVD-GSTRI; CAUFVD-GSUZI; CAUFVD-GETRI; CAUFVD-GEUZI; , KBA , PP-SFC-EXE-CON , Confirmation , Problem