2613072 - Reorder point MRP planning does not consider planning horizon

Symptom

If MRP type is 'Reorder Point', eg. MRP type V1, VB etc., the MRP run with Processing Key 'NETPL' (Net Change in Planning Horizon) does not consider the planning horizon. In this case the system covers the requirements also which are outside the planning horizon.


Read more...

Environment

  • SAP ERP Production Planning (PP)
  • SAP R/3
  • SAP R/3 Enterprise
  • SAP ERP Central Component
  • SAP ERP
  • SAP Enhancement package for SAP ERP
  • SAP Enhancement package for SAP ERP, version for SAP HANA
  • SAP S/4HANA, on-premise
  • SAP S/4HANA, cloud edition

Product

SAP ERP Central Component all versions ; SAP ERP all versions ; SAP R/3 Enterprise all versions ; SAP R/3 all versions ; SAP S/4HANA Cloud all versions ; SAP S/4HANA all versions ; SAP enhancement package for SAP ERP all versions ; SAP enhancement package for SAP ERP, version for SAP HANA all versions

Keywords

MM-CBP, PP-MRP, MRP, Reorder Point, Planning Horizon, External reqmts within replenishment lead time, Processing Key, NETPL, Net Change in Planning Horizon, OMDQ, MRP type V1, VB, MRP procedure, Bestellpunktdisposition, Plangesteuerte Disposition, Planungshorizont, Externe Bedarfe innerhalb der Wiederbeschaffungszeit, Verarbeitungsschlüssel, Net-Change im gesamten Horizont , KBA , MM-CBP , Consumption-Based Planning , PP-MRP , Material Requirements Planning , Problem