2531898 - CJ20N: unable to change WBS element once project is released

Symptom

In transaction CJ20N, the project definition (PRPS-POSID) and WBS element (PRPS-PSPID) fields become grayed out after setting the System Status to released (REL). Therefore, you are unable to rename or change these fields.


Read more...

Environment

  • SAP ERP Project System (PS)
  • SAP R/3
  • SAP R/3 Enterprise
  • SAP ERP Central Component
  • SAP ERP
  • SAP Enhancement package for SAP ERP
  • SAP Enhancement package for SAP ERP, version for SAP HANA
  • SAP S/4HANA, on-premise
  • SAP S/4HANA, cloud edition

Product

SAP ERP Central Component all versions ; SAP ERP all versions ; SAP R/3 Enterprise all versions ; SAP R/3 all versions ; SAP S/4HANA Cloud all versions ; SAP S/4HANA all versions ; SAP enhancement package for SAP ERP all versions ; SAP enhancement package for SAP ERP, version for SAP HANA all versions

Keywords

CJ02, code, ID, greyed out, Status I0002, uneditable, ALE distribution, identification, re-name, cannot edit, POSID, PSPID , KBA , PS-ST-WBS , Work Breakdown Structure , PS-ST , Structures , PS-SIM , Simulation , PS-ST-DEF , Project Definition , Problem