2459208 - Planned order missing requirements after key completion

Symptom

Your planned order is missing requirements/components after key completion.

MissingReq.PNG

The same order has all its requirements/components in ECC.

ReqInECC.PNG

The components can still be seen in the PDS through /SAPAPO/CURTO_SIMU.

ComponentsPDS.PNG


Read more...

Environment

  • SAP Supply Chain Management (SCM)
  • SAP Advanced Planning and Optimization (SCM-APO)
  • SAP enhancement package for SAP Supply Chain Management

Product

SAP Supply Chain Management 2005 ; SAP Supply Chain Management 2007 ; SAP Supply Chain Management 4.0 ; SAP Supply Chain Management 4.1 ; SAP Supply Chain Management 7.0 ; SAP enhancement package for SAP Supply Chain Management all versions

Keywords

Missing Requirements, Missing Components, Planned Order, Key Completion, Missing, Requirements, Components  , KBA , SCM-APO-INT-PPS , PP-DS / Production and Process Order , Problem