2426853 - Selected Resource is not used as active mode in new planned orders

Symptom

  • In the Detailed Scheduling Planning Board (/SAPAPO/CDPS0), you right click a Resource in the Resources Chart and choose Create Order option
    • At this point, you realize that the activity was not scheduled in the selected Resource, but in an alternative mode

  • The same issue occurs when you select the Resource and go to menu Functions -> Order -> Create...

Read more...

Environment

  • SAP Supply Chain Management Production Planning and Detailed Scheduling (SCM-APO-PPS)

Product

SAP ERP, add-on for embedded production planning and detailed scheduling all versions ; SAP Supply Chain Management all versions ; SAP enhancement package for SAP Supply Chain Management all versions

Keywords

Create Order..., /SAPAPO/SAPLCDPS_FUNC_DISPATCH, ORDER_CREATE, /SAPAPO/LCDPS_FUNC_DISPATCHF02, /SAPAPO/CDPS1, /SAPAPO/CDPS2, /SAPAPO/CDPS3, mode selection , KBA , SCM-APO-PPS-DST , Detailed Scheduling Planning Board , Problem