2423713 - Incorrect values on WBS in PS reporting | SAP Knowledge Base Article

SAP Knowledge Base Article - Preview

2423713 - Incorrect values on WBS in PS reporting

Symptom

When running Project Systems (PS) reports, costs (planned/actual) from deleted network activities are displayed on WBS level.


Read more...

Environment

  • SAP ERP Project System (PS)
  • SAP R/3
  • SAP R/3 Enterprise
  • SAP ERP Central Component
  • SAP ERP
  • SAP Enhancement package for SAP ERP
  • SAP Enhancement package for SAP ERP, version for SAP HANA
  • SAP S/4HANA, on-premise
  • SAP S/4HANA, cloud edition

Product

SAP ERP Central Component all versions ; SAP ERP all versions ; SAP R/3 Enterprise all versions ; SAP R/3 all versions ; SAP S/4HANA Cloud all versions ; SAP S/4HANA all versions ; SAP enhancement package for SAP ERP all versions ; SAP enhancement package for SAP ERP, version for SAP HANA all versions

Keywords

KPOR_DEL_ORDER_CORRECT, planned, S_ALR*, DLFL, rolled-up, COSP, COSS, Network, CJ20N, RPSCO, cost element, hierarchy, actual cost, S_ALR_87013570, COSSP, CJEN, OLC, LOG_EAM_OLC, LOG_EAM_OLC2, OPJB , KBA , PS-COS-PLN-PLN , Planned Costs , PS-COS-ACT , Actual Costs and Forecast , PS-IS , Information System , How To

About this page

This is a preview of a SAP Knowledge Base Article. Click more to access the full version on SAP ONE Support launchpad (Login required).

Search for additional results

Visit SAP Support Portal's SAP Notes and KBA Search.