2387910 - Scheduling in Non-Working times of a Secondary Capacity

Symptom

  • You use secondary capacities in APO
  • When you create a Planned Order, you notice that the activity on the Secondary Capacity is scheduled during Non-Working Time of this Resource
  • You are able to Drag&Drop an activity on the Primary Resource at a point where the Secondary Resource is not working

Read more...

Environment

  • SAP Supply Chain Management Production Planning and Detailed Scheduling (SCM-APO-PPS)

Product

SAP ERP, add-on for embedded production planning and detailed scheduling all versions ; SAP Supply Chain Management all versions ; SAP enhancement package for SAP Supply Chain Management all versions

Keywords

Calendar Resource, Primary Resource, Secondary Resource, SETCALE, MAIN_RESOURCE, TSTREAM_RESOURCE, non working time , KBA , scm , SCM-APO-PPS-SCF , Scheduling Functions , SCM-APO-PPS , Production Planning and Detailed Scheduling , Problem