2168144 - Wrong delivery date in MD04 after rescheduling | SAP Knowledge Base Article

SAP Knowledge Base Article - Preview

2168144 - Wrong delivery date in MD04 after rescheduling

Symptom

  • MD04 shows the requirement date and the required quantity, but not the confirmed date and confirmed quantity in supplying plant.
  • Your expectation is that the committed quantities and committed dates of the STO are taken into account in MD04.
  • You want that schedule lines of STO should be displayed as per schedule lines of availablility check (confirmed schedule lines) in suppying plant.
  • System display only first schedule line data in supplying plant.

Read more...

Environment

  • Materials Management (MM)
  • SAP R/3
  • SAP R/3 Enterprise 4.7
  • SAP ERP Core Component
  • SAP ERP
  • SAP enhancement package for SAP ERP
  • SAP enhancement package for SAP ERP, version for SAP HANA

Product

SAP ERP all versions ; SAP R/3 all versions ; SAP enhancement package for SAP ERP all versions ; SAP enhancement package for SAP ERP, version for SAP HANA all versions

Keywords

ECC, md04, supplying, wrong, ATP, checking rule, wrong, missing, dates, co09, rescheduling, shipment , KBA , MM-PUR-GF-STO , Stock Transfer , MM-PUR-GF-ATP , Availability check , Problem