2145487 - ChaRM: How to check allowed actions for each phase of a Cycle - Solution Manager

Symptom

  • 'Schedule Import Job for Transport Requests' task errors with: Action SM_IMP_TEST is not allowed in this phase when phase is Go-Live
  • Error: Unable to successfully complete import into production system.  Action SM_IMP_PROD is not allowed in this phase
  • The phase of the Cycle restricts the available actions for Normal Change, Urgent Change and also jobs in task list.
  • Action to be checked: SM_IMP_PROD; Action SM_IMP_PROD is not allowed in this phase

For example, scheduling import to production system in task list is not allowed when Phase Cycle (in 7.10, Maintenance Cycle) is in phase 'Build' (in 7.10, 'Development without release')
In 7.20, the Monitor > Messages will show the error:
action is not allowed in this phase.png


In 7.10, there will be a popup when try to schedule import to production system:
Notallowed.png
Task cannot be executed/schedule during phase 'Development without Release'

 


Read more...

Environment

SAP Solution Manager

Product

SAP Solution Manager all versions

Keywords

Phase, Preliminary Import, Maintenance Cycle, , KBA , SV-SMG-CM , Change Request Management , How To