2113997 - Float of a completed task - Critical Path

Symptom

When the status of a released task is set to "complete" - the float is set to 0 and then the task is part of the critical path in Gantt-Graphic.


Read more...

Environment

Portfolio and Project Management (PPM)

Product

SAP Portfolio and Project Management 5.0 ; SAP Portfolio and Project Management 6.0 ; SAP Portfolio and Project Management 6.1

Keywords

kritischer Pfad, Puffer, abgeschlossen, Aufgabe, Grafiksicht, rot, CL_DPR_SCHEDULING_SERVICES, CALCULATE_DATES, CL_DPR_UI_LOG_GANTT, CONVERT_DETAIL_DATA, TOTAL_FLOAT , KBA , PPM-PRO , Project Management , Problem