SAP Knowledge Base Article - Public

3088030 - Professional Services: Issue with Exchange rate type when copying Internal / Customer Project

Symptom

When you copy a project where the Project currency is different from Currency of the Service Org. company code, then the initial planned cost rate of the newly copied project uses the exchange rate “M” (Standard translation at average rate) instead off “P” (Standard translation for cost planning).

Environment

SAP S/4HANA Cloud 2108

Reproducing the Issue

  1. Open Plan Customer Project app (or) Plan Internal Project app.
  2. Select a Project where Service Organization currency and Project Currency are different and it contains work package with plans (Teams / Additional Resources)
  3. Copy and Save the project.
  4. Planned Cost in the Work packages and Projects is calculated using exchange rate “M”.

Cause

Due to technical error, Default exchange rate “M” is considered for calculation of planned cost.

Resolution

Recalculate each work package to refresh the planned cost based on the exchange rate “P”.

Keywords

Commercial Project, Plan Cost, Copy Project , KBA , CA-CPD-SS , S/4HANA Professional Services Cloud - CPM , Known Error

Product

SAP S/4HANA Cloud 2108