Symptom

Cannot change the Responsible Unit once Project Task is Released

Environment

SAP Business ByDesign

Reproducing the Issue

  1. Go to the Project Management work center.
  2. Go to the Projects view.
  3. Search and open the Project ABC (ABC represents the Project ID).
  4. Click on the View All button.
  5. Select the respective Project Task.
  6. Go to the Accounting tab. 

Responsible Unit field is greyed out.

Cause

Once the Task is Released, there is no possibility to maintain it from UI and neither from the backend, because this information is replicable in Costing (Financials) and hence it is not possible to perform the change.

Resolution

We suggest for this case to close the Project Task and create a new one with the correct responsible unit.