Symptom
When there are multiple billing due date in the past, in manage project billing app, they will always be summed up.
Environment
SAP S/4HANA Cloud
Reproducing the Issue
- Create a customer project with billing WBS element (fixed price).
- Maintain 2 billing due date in the past.
- Go to manage project billing app.
- The amount of the 2 billing due date will always be summed up.
Cause
Currently, it is standard behavior.
Resolution
This is going to be improved in the future release. (It has not been decided in which release)
In order to create separated project billing request (PBR), as a workaround, one billing due date can be removed from the billing WBS element.
After creating one PBR, add the billing due date then create another PBR.
Keywords
manage project billing, billing due date, customer project , KBA , PS-FIO , Fiori UI for Project System , Problem
Product
SAP S/4HANA Cloud all versions