Symptom

In app "Manage project procurement", the delivered quantity is shown as twice the ordered quantity.

Environment

SAP S/4HANA Cloud 2008

Reproducing the Issue

  1. Open a stock transfer order in "change purchase order" app.
  2. Perform availability check for an item to create another schedule line. 
  3. Check the stock transfer order in app "Manage project procurement", the delivered quantity is shown as twice the ordered quantity.

Cause

Known issue

Resolution

The correction will be available as part of S/4HANA Cloud CE2011.