SAP Knowledge Base Article - Preview

2891519 - Shipping Date is not calculated for some of the PO items when PO received in SNC

Symptom

In SNC-ERP PO collaboration scenario, shipping date after past line item doesn’t have shipping date in PO.

For example, if PO created for 3 line items, shipping date past in the first line item then the 2nd and the 3rd line items have no shipping date displayed; if PO created with for 3 line item, shipping date past in the 2nd line item then the 3rd line item onwards you will not see shipping date.


Read more...

Environment

  • SAP Supply Network Collaboration (SCM-ICH)
  • SAP Supply Chain Management (SCM)
  • SAP enhancement package for SAP Supply Chain Management

Product

SAP Supply Chain Management all versions ; SAP Supply Network Collaboration all versions ; SAP enhancement package for SAP Supply Chain Management all versions

Keywords

PO_SHIP_DATETIME_IN_PAST, POC1, PO collaboration in SNC, Shipping Date, PurchaseOrderERPReplenishmentOrderCollaborationNotification_In, inbound process. , KBA , SCM-ICH-PO , Purchase Order and Replenishment Order , Problem

About this page

This is a preview of a SAP Knowledge Base Article. Click more to access the full version on SAP ONE Support launchpad (Login required).

Search for additional results

Visit SAP Support Portal's SAP Notes and KBA Search.