2828944 - How to reactivate an inactive Work Item in Plan Customer Projects

Symptom

You notice that a Work Item from a Work package is shown as Inactive. Since this Work package is inactive when you try to do a change to a work package message Please choose a different work item. xxxxxx is inactive.

Environment

SAP S/4HANA Cloud

Reproducing the Issue

  1. Go to Plan customer projects.
  2. Select a Project and click Edit.
  3. Go to the Work Packages tab.
  4. Select one Work Package.
  5. Make changes to this Work Package and click Save.

Cause

The Work Item is inactive.

Resolution

To Reactivate the work item, please follow the steps below:

  1. Go to the Work packages tab.
  2. Click the Work item for the desired Work Package.
  3. Click Edit.
  4. Uncheck the Work Item that is Inactive.
  5. Click Ok
  6. Save.

Keywords

  Work Item, Work Package, Plan customer projects, Project, Save, inactive, reactivate , KBA , CA-CPD-SS , S/4HANA Professional Services Cloud - CPM , Problem