2816010 - Project Builder app: navigation to AuC missing

Symptom

On-premise transaction CJ20N has menu path 'Edit' → 'WBS element' → 'Investment programs' → 'Asset under construction' (AuC) in case of investment projects. The same functionality is expected in Fiori apps Project Builder and Project Control.

Environment

  • SAP ERP Project System (PS)
  • SAP S/4HANA Cloud 

Cause

The navigation (from 'Edit' → 'WBS element' → 'Investment programs' → 'Asset under construction') is not available in cloud applications Project Builder and Project Control.

Resolution

As an alternative for your requirement, app "Project Planning" can be used to see the ID's of the created AuC's even on lower level WBS-elements.

See Also

Fiori apps library: Project Planning

Keywords

PSP, Project Planning, F3822 , KBA , PS-FIO , Fiori UI for Project System , PS-ST-PB , Project Builder , IM-FA-PR , Investment projects , How To

Product

SAP S/4HANA Cloud all versions