Symptom

Message "The cost center is not valid for these dates" is displayed when trying to create an internal project.

Environment

SAP S/4 HANA Cloud
SAP Commercial Project Management (CPM)

Reproducing the Issue

  1. Go to App: Create Internal Projects
  2. Error-Message is displayed: The cost center is not valid for these dates.

Cause

There is no cost center configured for the service organization.

Resolution

  1. Go to App: Maintain Service Organizations
  2. Open the Service Organization in Edit-Mode
  3. Select in the drop-down field "Default Cost Center"
  4. Save changes.