Symptom
If you set for scheduling 1 Period start := delivery date in OMI4, MRP run (e.g.: MD01, MD02, MD03), it gives same result when you set for scheduling 2 Period end := delivery date.
Read more...
Environment
- SAP ERP Production Planning (PP)
- SAP R/3
- SAP R/3 Enterprise
- SAP ERP Central Component
- SAP ERP
- SAP Enhancement package for SAP ERP
- SAP Enhancement package for SAP ERP, version for SAP HANA
- SAP S/4HANA, on-premise
- SAP S/4HANA, cloud edition
Product
SAP ERP Central Component all versions ; SAP ERP all versions ; SAP R/3 Enterprise all versions ; SAP R/3 all versions ; SAP S/4HANA Cloud all versions ; SAP S/4HANA all versions ; SAP enhancement package for SAP ERP all versions ; SAP enhancement package for SAP ERP, version for SAP HANA all versions
Keywords
PP-MRP, delivery date, scheduling, customizing, OMI4, MD04, MD01, MD02, MD03, period, daily lot, same result, mrp run, Tageslosgröße, Terminbestimmung, Periodenanfang, Periodenende, Verfügbarkeitstermin , KBA , PP-MRP , Material Requirements Planning , Problem