Symptom
You made "status dependent import" settings in /TMWFLOW/VC_IMPS via SM34 for relevant project,status,transaction type.
For example like below:
But when you start project import in tasklist,you found not only the TRs in correct status(Change Doc),
other all TRs not in the relevant status of change doc also imported into the target system.
Read more...
Product
SAP Solution Manager 7.1
Keywords
Status dependent import; SAP0; variant for project import; /TMWFLOW/MAINTINST; SM34;/TMWFLOW/VC_IMPS;Proejct import;Schedule Import Job for Transport Requests; , KBA , SV-SMG-CM , Change Request Management , Problem
About this page
This is a preview of a SAP Knowledge Base Article. Click more to access the full version on SAP ONE Support launchpad (Login required).Search for additional results
Visit SAP Support Portal's SAP Notes and KBA Search.